NETCO COMPLETES FEED/DED PHASE OF CNL ROBERTKIRI GAS PROJECT By Engr. (Mrs) W.H. Inyang

Chevron Nigeria Limited (CNL) executed a combined Front End Engineering Design/Detailed Engineering Design (FEED/DED) in support of its plan to produce gas (Associated Gas, AG and Non-Associated Gas, NAG) from existing and new wells to be drilled to maintain the gas production plateau at Robertkiri and Idama for further sales to third party.

 

The Robertkiri field is located in the swamp area of the Niger Delta, 35 Km southwest of Port Harcourt.

The goals of the project are to achieve Associated Gas flare out and develop Non-Associated Gas resources. This entails modification of the piping on the primary separation process and installation of sales gas metering devices at Robertkiri and Idama Production Platforms.

To meet these goals, CNL planned to revamp Five (5) existing wells, two (2) of which are dual completions and also drill two (2) new NAG wells.

 

Robertkiri Platform (Insert: NETCO Engineer taking readings)

 

NETCO's scope of work included the following activities:

·         Designing of two (2) new Flowlines from the two (2) new wells to the Robertkiri Platform

·         Review of existing topside configuration and validate the modifications that are required for CNL to achieve its objectives.

·         Installation of new sales gas metering devices, Heat Exchanger, Hot Oil System and Flash Separator on the topsides of Robertkiri Production Platform.

·         Provision of HP and LP tie in flanges for a third party gas export line connection.

Other activities carried out during the execution of the project included; Site Visit, Constructability review and Process Hazard Analysis (PHA) review.